Cladding crisis notice is light on detail

Government plans to claim £4bn from property developers to fix cladding issues are ‘light on detail’ and ‘important questions remain unanswered’, says Peter McHugh.

Peter McHugh, partner in our construction team, says with the threat of legal action hanging over developers the government should be providing clarity as a matter of urgency.

What does this mean for developers?

Earlier this month, housing secretary Michael Gove, announced developers would have to contribute around £4bn to replace dangerous combustible cladding on mid-rise buildings (those between 11 and 18m in height). In addition, the government plans to introduce legislation that would retrospectively extend the legal right of building owners and leaseholders to demand compensation from their building’s developer for safety defects up to 30 years old.

At a summit with Gove on 20 January, senior executives from 20 building firms said the government and companies that sold combustible materials must shoulder some of the blame.

“If developers fail to contribute, the government has said it will “take all steps necessary” to deliver the remediation work,” said Peter, who specialises in construction, property and engineering law.

“This could include restricting access to government funding and future procurements, pursuing companies through the courts, and the imposition of a solution in law.”

What questions remain unanswered?

However, “the government notice is light on detail and important questions remain unanswered.

These include:

  • When will developers discover they are within the scope of companies expected to contribute?
  • What level of financial contribution does the government expect from developers?
  • Will remediation work, already undertaken by developers, result in a reduction to an expected contribution?
  • Will the government demand similar contributions from the manufacturers of defective cladding products?
  • Will the government seek further contributions to cover wider not-cladding safety issues such as flammable balconies, that campaigners have asked for?
  • Will buildings under 11m in height be included in the future?
  • Will the funding be distributed via the existing Building Safety Fund, or will a new fund and application process be set up?

It is not clear when, or if, these questions will be answered, especially if the government expects a “clear, fully funded plan of action” by March 2022.”

What are the current uncertainties?

Meanwhile, Peter says the occupiers of mid-rise properties with cladding issues are also living with the uncertainty.

“Despite pressure on the government to ban the use of combustible materials in mid-rise buildings the use of such materials remains allowable under the current regulations,” he added.

“This has led to bizarre situations where new-build mid-rises are being built using combustible materials, but existing mid-rises are seeking removal of their cladding systems after External Wall Fire Review (EWS1) surveys have highlighted dangers posed by the materials and construction.”

Michael Gove’s Government Approach to Building Safety letter on January 10, stated he was putting developers on notice over cladding issues and pledged that leaseholders living in developments above 11 metres would no longer have to pay to fix safety problems.

Contact our Construction legal experts

You can get in touch with our Construction law specialists by requesting a consultation.

Posted:

Your key contact

Peter McHugh

Partner & ADRg Accredited Mediator

Birmingham
Peter McHugh is a construction law specialist, acting on behalf of contractors, sub contractors and employers in disputes of all sizes and types.
View profile for Peter McHugh >

More on this topic

Property litigation

Ban on leasehold houses

As anticipated, the proposed ban on leasehold houses was a late addition to the Leasehold and Freehold Reform Bill (‘the Bill’).
Read more on Ban on leasehold houses
Social housing

Case law update – Courts pivot to mandatory dispute resolution

On 29 November 2023, the Court of Appeal handed down judgement in the matter of Churchill v Merthyr Tydfil County Borough Council  [2023] EWCA Civ 1416 confirming that the court can stay claims and compel parties to engage in alternative dispute resolution.